What problems should be paid attention to in the operation of open close current transformer
Jul 13, 2022| 1) The current transformer manufacturer shall not open the secondary side during operation. Once the secondary side is opened, it will lead to insulation breakdown due to excessive iron loss and high temperature, or the voltage of the secondary winding will rise, which will lead to the risk of high-voltage electric shock. Therefore, when replacing the ammeter, such as the ammeter, active meter, reactive meter, etc., the current circuit should be short circuited before replacing the ammeter. After the instrument is adjusted, connect the instrument to the secondary circuit first, and then unplug the short wire to check whether the instrument is normal.
2) If sparks are found when removing the short-circuit line, the short-circuit should be re short circuited immediately after opening the CT. The short circuit can be removed again only when it is found that there is no open circuit in the instrument circuit. When removing the CT short circuit, the protective device should be placed on the insulating leather pad. In addition, it should be considered to stop using the protection device of CT circuit. After the work is completed, the protective device can be put into use.
3) If the current transformer buzzes, check whether the internal iron core is loose and tighten the iron core bolts. One end of the secondary side of the current transformer and the shell shall be reliably grounded.
4) When the insulation resistance of the secondary coil of the current transformer is lower than 10~20 megohm, it should be dried and restored before use.