How to ensure that the ratio test of the current transformer is within the allowable range?
Aug 06, 2025| 1. Preparation before testing
1. Disconnect the load: Disconnect the load on the secondary side of the current transformer to ensure the safety of the test environment.
2. Check the equipment: Make sure that the appearance of the current transformer is not damaged, and the terminal is not loose or corroded.
3. Prepare the test instrument: Use a professional ratio tester to ensure that the accuracy of the test instrument meets the requirements.
2. Test steps
1. Connect the test instrument: Connect the output line of the ratio tester to the primary side of the current transformer, and connect the measuring line to the secondary side.
2. Apply current: Set the tester output current to the specified value, usually the rated current of the current transformer.
3. Read data: Read and record the current values of the primary and secondary sides, and calculate the ratio value.
4. Compare the rated ratio: Compare the actual measured ratio with the rated ratio of the current transformer to determine whether it is within the allowable error range.
3. Judgment criteria
1. Allowable error range: According to the accuracy level of the current transformer, the ratio error should be within a certain range. For example, in a 0.2-level current transformer, the ratio error range should be within 0.2%; in a 0.5-level current transformer, the ratio error range should be within 0.5%.
2. Technical requirements: The ratio error should not exceed 3%, and the current transformer for measurement should meet the factory technical standards.
IV. Precautions
1. Test instrument grounding: Pay attention to the grounding safety of the test instrument to avoid personal or equipment safety accidents caused by equipment failure or improper operation.
2. Short-circuit unmeasured windings: For current transformers with multiple windings in the secondary, if the measured secondary current error is large, it may be that other secondary circuits are open, causing CT flux saturation. At this time, other unmeasured secondary windings should be short-circuited.
3. Record test results: Record the test results in detail, including the test date, test instrument model, test data, etc., for subsequent analysis and reference.