How to Install the Secondary Side of an Open-Type Current Transformer

Aug 05, 2026|

I. Pre-Installation Preparation
1. Select copper core secondary conductors with a cross-sectional area ≥ 2.5mm², ensuring the conductors are undamaged and free of breaks.

2. Prepare appropriate insulating tools, a multimeter, and a dedicated shorting clip. Do not use ordinary conductors as substitutes for shorting clips.

3. Ensure the measuring/protection equipment at the secondary side is de-energized to avoid accidental contact with live terminals during wiring.

II. Core Installation Steps
1. First, reliably connect the S1 and S2 terminals of the current transformer's secondary side directly to the corresponding terminals of the downstream instruments/protection devices using conductors, maintaining circuit continuity throughout.

2. Use a multimeter to test the continuity of the secondary circuit, confirming the circuit resistance is < 0.5Ω and there are no loose connections or breaks.

3. Reliably ground one end of the secondary circuit at a single point according to specifications, ensuring the grounding resistance meets safety standards.

4. After confirming the secondary side is completely closed without any open circuits, close the core opening of the current transformer to complete the fixed installation of the current transformer body.

III. Post-Installation Verification

1. Re-check the continuity of the secondary circuit to ensure there are no open circuit points throughout.

2. Check that all wiring terminals are securely fastened and that the secondary wires are neatly arranged without any pulling or wear.

3. Before powering on, confirm that no fuses, switches, or other easily disconnectable components are connected to the secondary circuit to completely eliminate any potential open circuit hazards.

What are the consequences of using an unsuitable current transformer?

Send Inquiry