Operation and maintenance management of residual current transformer

Jul 28, 2023|

(1) After the residual current transformer is put into operation, the user should establish operation records and corresponding management systems

(2) Power management personnel conduct a power-on trip test on the residual current transformer at least once a month, that is, press the test button to check whether the residual current transformer is reliable. When the leakage transformer operates due to lightning strike or other reasons, it should be checked and tripped. In the peak season of rural electricity consumption, the number of trips should be increased; the disabled residual current transformer should be tripped once before use.

(3) In order to fully grasp the operating status of leakage transformers, sampling inspections of leakage transformers should be carried out regularly (such as during annual safety inspections).

(4) The detection of the residual current transformer is organized and implemented by the full-time safety management personnel of the power supply station under the guidance of the local power department. The items for regularly testing the operating characteristics of residual current transformers should include residual operating current value, remaining non-operating value, and breaking time.

(5) The low-voltage power grid test content includes the protected power grid, the protected power grid and various load-to-ground unbalanced leakage currents, motor insulation resistance, neutral point leakage current on the low-voltage side of the distribution transformer, and power consumption of each power grid. quantity. The earthing resistance of the equipment protective earthing device. Compare the test data with the previous test results for comprehensive analysis. Those that fail to pass the test or have major defects should be repaired or replaced in time.

(6) The operation characteristic test of the residual current transformer and the simulated leakage operation test of the protective grid should be carried out by professionals using special measuring instruments qualified by the relevant state departments. It is strictly forbidden to use the phase line to directly contact the grounding device for the simulated leakage action test of the protection grid.

(7) The process of jumping, testing, setting and testing must be recorded by a special person, and the recorded items and data must not be confused or wrong, for future operation and analysis reference.

(8) If an electric shock casualty accident occurs within the protection range of the leakage current transformer, the action of the protector should be checked, the cause should be analyzed, and an accident report should be written. Note: Before the power department sends personnel to inspect, the site must be protected, and the protected site must not be changed.

(9) If the user intentionally causes the protector to not operate or malfunction, it shall be criticized, educated and warned. Those who still do not repent after being criticized and educated can temporarily stop household electricity use.

(10) After the residual current transformer is in operation, if the cause of the accident is not found through inspection, a trial power transmission is allowed. Unless the residual current transformer itself is faulty after inspection, it is strictly forbidden to disassemble the residual current transformer and force the power supply.

(11) The maintenance of the residual current transformer should be carried out by professionals. If any abnormal phenomenon occurs during operation, an electrician should be consulted to avoid expanding the scope of the accident.

(12) The power supply station should be equipped with general test instruments and a certain number of backup protectors. The operation of the leakage transformer should be analyzed regularly, and the leakage transformer that cannot be used normally should be replaced in time.

Send Inquiry